As part of the Annual Street Resurfacing Program, the City will be paving Gardens East Dr. beginning July 18, 2016 for approximately five (5) days, weather permitting. The project will be completed in three phases.
Phase I- Paving from Burns Road to approximately 900 feet south with a full road closure (local traffic only) on July 18, 2016 beginning at 9 p.m. to 6 a.m. Motorists will be detoured to an alternate route.
Phase II- Paving from 900 feet south of Burns to Lighthouse Drive with partial lane closures in both directions.
Phase III- Paving Burns Rd. to RCA Dr. with partial lane closures in both directions. Motorists should expect delays.
For further information, please contact Louis Johnson, Operations Manager/Streets & Stormwater, at (561) 804-7048.